Construction
Update

Silverwell is under construction!
Check this page for regular updates
on how each stage is progressing.

Stage One

100%

Civil Construction

100%

Title Registration

1%

Home Build

Less
CIVIL CONSTRUCTION PHASE STATUS
Bulk Earthworks Complete
Drainage Complete
Sewer Complete
Water & Gas Services Complete
Road Boxing, Kerb & Channel Complete
Electrical & Telecommunications Complete
Footpaths & Laneways Complete
Asphalt Complete
Signage & Topsoil Complete
TITLE REGISTRATION PHASE STATUS
Practical Completion/Audits Complete
Statement of Compliance Issued
Titles Issued 12 January 2023
HOUSE BUILD COMMENCEMENT STATUS
Underway *Commenced April 2023

*With all lots settled in Stage 1, house construction will commence as per the terms of the building contract.

A representative from TownLiving will be in touch regarding the build, though please ensure that following settlement you provide them with a copy of your title and any other information required under the building contract.

HOUSE CONSTRUCTION COMMENCED

House construction in Stage 1 is in full swing and we are excited that some residents will soon be calling Silverwell home with the first phase of house builds nearly complete.

The team at TownLiving will be in touch with individual owners to provide updates around the progress of your house.

Stage 2

90%

Civil Construction

0%

Title Registration

0%

Home Build

More
CIVIL CONSTRUCTION PHASE STATUS
Bulk Earthworks Complete
Drainage Complete
Sewer Complete
Water & Gas Services Complete
Road Boxing, Kerb & Channel Complete
Electrical & Telecommunications Complete
Footpaths & Laneways In progress
Ashphalt In progress
Signage & Topsoil In progress
Intersection In progress
TITLE REGISTRATION PHASE STATUS
Practical Completion/Audits Dec 2023 / Jan 2024
Statement of Compliance January 2024
Titles January 2024
HOUSE BUILD COMMENCEMENT STATUS
Construction Commences Forecast Early 2024**

** House construction will commence following the completion of the stage and settlement on the land as per the terms of the land contract and building contract.

CONSTRUCTION COMMENCED

Although internal concrete works and top-soiling continued this week, the works were hampered by the weather. As such, some lots will not be top-soiled and pegged by 7th December as previously anticipated for valuers. Valuers for lots 1-23 (inclusive) will still be able to view the lots on 7th and 8th December 2023, though valuers for lots 24-29, 54-64 and 86-96 (all inclusive) will need to push their inspections back a week to the 14th and 15th December. Please contact Core for more details regarding valuer access.

These minor delays however have not impacted the critical intersection works or other key dates, with most of the kerb and channel now in place, with the balance to be completed next week with the pouring of the bus bay and completion of the footpath. The base layer of asphalting is still anticipated for the second week of December, which will see the intersection nearing completion.

Whilst works are nearing completion and will typically be complete before the year’s end, authority audits are also required and given timeframes around those actions will anticipate we will not see titles issued until January 2024.